Table of contents
Page
Summary of Main Works Undertaken and Key Measures Implemented
Summary of Exceedances, Investigation and Follow-up
Complaint Handling, Prosecution and Public Engagement
Review of Status and Location of Monitoring Stations
Construction Activities undertaken during the Reporting Month
Status of Environmental Licensing and Permitting
Monitoring Parameters and Frequency
Comparison of EM&A Result with EIA Prediction
Monitoring Parameters, Frequency and Duration
Monitoring Methodology and QA/QC Procedure
Comparison of EM&A Result with EIA Prediction
Implementation Status of Environmental Mitigation Measures
Implementation Status of Event and Action Plans
Status of Required Submission under Environmental Permit
11 Environmental
non-conformance
Summary of Complaint, Warning, Notification of any Summons and Successful
Prosecution
13 Conclusions
and recommendations
lIST OF TABLES
Table I Summary
of Key Construction Work in the Reporting Month
Table II Summary
of Key Mitigation Measures Implemented in the Reporting Month
Table III Summary of Complaint/Summons/Prosecution in the Reporting Month
Table IV Summary Table for Site Activities in the next Reporting
Period
Table V Summary Table for Review of Status and Location of Monitoring Stations
Table 1.1 Key Project Contacts
Table 1.2 Summary
of Key Construction Work in the Reporting Month
Table 1.3 Summary
of Environmental License and Permit
Table 2.1 Air Quality Monitoring Locations
Table 2.2 Frequency and Parameters of Air Quality Monitoring
Table 2.3 Air Quality Monitoring Equipment
Table 2.4 Major Dust Source during Air Quality Monitoring
Table 2.5 Comparison of 1-hr TSP Monitoring Data
with Predictions in EIA Report (not used)
Table 2.6 Comparison of 24-hr TSP Monitoring Data
with Predictions in EIA Report
Table 3.1 Noise Monitoring Stations
Table 3.2 Frequency and Parameters of Noise Monitoring
Table 3.3 Noise Monitoring Equipment
Table 3.4 Major Noise Source during Noise Monitoring
Table 3.5 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Table 3.6 Comparison of Noise Monitoring Data with Predictions in EIA Report
Table 7.1 Construction Phase Landscape and Visual Mitigation Measures
Table 7.2 Construction Phase Audit Checklist for Landscape and Visual Mitigation Measures
Table
10.1 Observations and
Recommendations of Site Audit
Table
10.2 Status of Required Submission under Environmental Permit
Table 12.1 Summary Table for Site Activities and the Key Environmental Issues in the next Reporting Period
lIST OF
FIGUREs
Figure 1.1 Layout Plan of the Project Site
Figure 1.2 Project
Organisation for Environmental Monitoring and Audit
Figure
2 Locations of Air Quality and Construction Noise
Monitoring Stations
lIST OF
APPENDIces
Appendix
A Action and Limit Levels
Appendix
B Environmental Monitoring Schedules
Appendix
C Copies of Calibration Certificates
for Air Quality Monitoring
Appendix
D Weather Information
Appendix E 1-hour TSP Monitoring Results and Graphical Presentations (not used)
Appendix
F 24-hour TSP Monitoring Results and
Graphical Presentations
Appendix
G Copies of Calibration Certificates
for Noise Monitoring
Appendix
H Noise Monitoring Results and Graphical Presentations
Appendix
J Event and Action Plans
Appendix
K Environmental Mitigation
Implementation Schedule (EMIS)
Appendix
M Summary of Exceedance
Appendix
N Tentative Construction Programme
Appendix
O Waste Generated in the Reporting
Month
1.
This is the 60th Environmental Monitoring and Audit
(EM&A) Report prepared by the Environmental Team (ET), Cinotech Consultants
Ltd., for “Trunk Road T2”. This report summarized
the monitoring results and audits findings of the EM&A programme under the
issued Environmental Permit (EP) No. EP-451/2013 and in accordance with the
EM&A Manual (AEIAR-174/2013) during the reporting month of February
2025.
Summary of Main Works Undertaken and
Key Measures Implemented
2.
The main works of each works contracts undertaken during the reporting
period are as follows:
Table
I
Summary of Key Construction Work in the Reporting Month
Contract No. |
Project Title |
Site Activities |
ED/2018/04 |
Trunk Road
T2 and Infrastructure Works for Developments at South Apron |
·
WVB – ABWF
works ·
WVB – E&M
works ·
WVB – External works ·
DPR – GRC panel subframe
installation ·
DPR – Parapet Installation ·
SUS – E&M works ·
LSCC – RC Structure ·
LSCC – Backfilling ·
TSS – WB internal structure
from CP22 to CP26 ·
TSS – EB internal structure
up to CP22 ·
CP – TSS WB Tympanum
construction |
ED/2020/03 |
Trunk Road
T2 - Traffic Control And Surveillance System (TCSS) and Associated Works
(1) |
·
WVB – Installation of TCSS
cable
containment, cable laying, power distribution, installation
of PA Speaker ·
WB & EB Tunnel
– Installation
of cable containment ·
Material delivery for TCSS
Sub- systems |
Notes: (1): No major construction work was undertaken
during reporting month. N/A: Not applicable |
3.
Implementation of the key mitigation measures during the reporting
period are as follows:
Table II
Summary of Key Mitigation Measures Implemented in the Reporting Month
Contract No. and Project
Title |
Key Mitigation Measures Implemented |
ED/2018/04 - Trunk Road
T2 and Infrastructure Works for Developments at South Apron |
Air Quality ·
Water spraying regularly on construction site area to
avoid dust generation. ·
Excavated dusty materials were covered by impervious
sheets. Noise ·
Air compressor was operated with door closed and have
valid noise labels. ·
Use of Quality Powered Mechanical Equipment (QPME) ·
Erecting noise barriers on site to minimize noise
impact generated from breaking activities. Water Quality ·
WetSep was constructed to treat the surface runoff
prior to discharge. Landscape and Visual ·
Tree protection zone was fenced off to protect the
existing tree. |
ED/2020/03 - Trunk Road
T2 - Traffic Control And Surveillance System (TCSS) and Associated Works
(1) |
N/A |
Notes: (1): No major construction work was undertaken
during reporting month. N/A: Not applicable |
Summary of Exceedances,
Investigation and Follow-up
4.
Exceedance of Action/Limit levels during the reporting month (February 2025)
and the investigation results and/or follow-up actions:
Air Quality Monitoring
·
No Action Level exceedance for 24-hour TSP was recorded.
·
No Limit Level exceedance for 24-hour TSP was recorded.
Construction Noise Monitoring
·
No Limit Level exceedance for day time construction noise was recorded
in this reporting month.
·
No Action Level exceedance was recorded in this reporting month.
Landscape and Visual Monitoring and Audit
·
No non-compliance of the landscape and visual impact was recorded in the
reporting month. The implementation of landscape and visual and mitigation
measures was checked by a Registered Landscape Architect (RLA) during the
environmental site inspections.
Complaint Handling, Prosecution and Public
Engagement
Table
III Summary of
Complaint/Summons/Prosecution in the Reporting Month
Event |
Event Details |
Follow-up/ Remedial Actions |
Status/ Remarks |
|
Number |
Brief Description |
|||
Complaints
Received |
0 |
- |
- |
- |
Notification
of Summons and Prosecutions Received |
0 |
- |
- |
- |
Public
Engagement Activities |
0 |
- |
- |
- |
5.
No reporting
change in this reporting month.
6.
The key works or activities
will be anticipated in the next reporting period are as follows:
Table
IV Summary Table for Site Activities
in the next Reporting Period
Contract
No. and Project Title |
Site Activities (March 2025) |
Key
Environmental Issues |
ED/2018/04 -
Trunk Road T2 and Infrastructure Works for Developments at South Apron |
·
WVB – ABWF works ·
WVB – E&M works ·
WVB – External works ·
DPR – GRC panel subframe
installation ·
DPR – Parapet installation ·
DPR – Sign gantry erection ·
SUS – E&M works ·
LSCC – RC Structure ·
LSCC – Backfilling ·
TSS – WB internal structure
from CP22 to CP26 ·
TSS – EB internal structure
up to CP22 ·
CP – TSS WB Tympanum
construction |
(A) / (B) / (C) / (D) |
ED/2020/03 -
Trunk Road T2 - Traffic Control And Surveillance System (TCSS) and Associated
Works (1) |
·
Project
signboard in works area |
|
Notes: (1): No major construction work was
undertaken during reporting month. N/A: Not
applicable (A)
Dust generation
from haul road, stockpile of dusty materials,
exposed site area, excavation works and rock breaking activities; (B)
Noisy construction activity such as
rock-breaking activities and piling works (C)
Runoff from exposed slope or site area; and (D)
Wastewater and runoff discharge from site. |
Review of Status and Location of Monitoring
Stations
7.
According to the
EM&A Manual (AEIAR-174/2013), the number and location of the monitoring
stations and parameters should be reviewed in every six months, or on as
-needed basis, in order to cater for any changes in the surrounding
environmental and the nature of works in progress. The latest review was
conducted in February 2025 and the review of status and location of monitoring
stations are summarized as follow:
Table
V Summary Table for Review of Status
and Location of Monitoring Stations
Monitoring
Station ID |
Review Status |
Follow-up
Action/ Recommendation |
KTD 2d |
ET has reviewed the status
and location of KER1, KTD 1, KTD2d, CKL1 and CKL2. To conclude, the
environmental monitoring conducted at KER1, KTD 1, KTD2d, CKL 1 and CKL 2 are
appropriate, and the monitoring results reflect how the sensitive receiver(s)
is/are impacted by the construction activities of the Project. |
N/A |
KER1 |
||
KTD 1 |
||
CKL 1 |
||
CKL 2 |
||
N/A: Not
Applicable |
1
INTRODUCTION
1.1
In 2009, Civil Engineering
and Development Department (CEDD) commissioned a Kai Tak
Development (KTD) – Trunk Road T2 and Infrastructure at South Apron
Investigation. The assignment
covers the provision of the Trunk Road T2 and its connections with the Central
Kowloon Route (CKR) at the north apron area and the Tseung Kwan O – Lam Tin
Tunnel (TKOLTT) to the south in the Cha Kwo Ling area.
1.2
The Trunk Road T2
Project is one of the designated Projects under Schedule 2 of the EIAO proposed
in the KTD. CEDD submitted the Project Profile (No. PP-379/2009) on 24 March
2009 for application for an EIA study brief for the Trunk Road T2 Project under
the EIAO. Accordingly, an EIA Study Brief (ESB-203/2009) for the Trunk Road T2
Project was issued on 30 April 2009. The Environmental Impact Assessment (EIA) Report for the Trunk Road T2
Project was approved under the Environmental Impact Assessment Ordinance (EIAO)
on 19 September 2013. The corresponding Environmental Permit (EP) was issued on
19 September 2013 (EP no.: EP-451/2013).
1.3
The Contract No.
ED/2018/04 is the main contract of Trunk Road T2 (“T2 Main Works”) which
comprises mainly the design and construction of a dual two-lane trunk road of
approximately 3.4km long with about 3.1km of the trunk road in form of tunnel;
ventilation and administration buildings, environmental protection and
mitigation works and etc. Moreover, the Contract No. ED/2020/03 is the other
contract under Truck Road T2 Project which comprises mainly design and
construction of the TCSS for this Project. The EM&A programme at Kai Tak
area under the Contract ED/2018/04 and ED/2020/03 are governed by the
EP-451/2013 and EM&A Manual (AEIAR-174/2013). The work areas of the Trunk
Road T2 Project are shown in Figure 1
and the works to be executed under each Contract and corresponding EP are
summarized as follows:
Environmental Permit |
Works Description |
EP-451/2013 –
Trunk Road T2 |
ED/2018/04 ·
Construction of highway and sub-sea tunnel
connecting between Central Kowloon Route and Cha Kwo Ling Tunnel ·
Western & Eastern Ventilation Buildings ED/2020/03 ·
Design and construction of TCSS for Trunk
Road T2 |
Monitoring Works in Kai Tak under
EP-451/2013
1.4
Under Contract No. KL/2014/03 – Kai Tak
Development – Stage 3 Infrastructure Works for Development at the Southern Part
of the Former Runway (“T2 Advance Works”), the baseline monitoring works in Kai
Tak under the EM&A Manual (AEIAR-174/2013) were conducted by the Environmental Team (ET) for the
Contract No. KL/2014/03 at the approved relocated monitoring locations (EPD
reference: EP2/K19/A/21 pt.5), namely KTD1a, KTD2a & KER1a. During the
impact monitoring period, monitoring locations KTD 2a and KER 1a were relocated
to new locations, i.e. KTD 2b and KER 1b (EPD reference: ( ) in EP2/K19/A/21 pt. 6 and ( )
in EP2/K19/A/21 pt. 5) respectively. Location KTD2b was then further relocated to location
KTD2c, the proposal of such relocation was submitted to EPD on 24 March 2020
and was approved by EPD on 6 April 2020 (EPD reference: ( ) in EP2/K19/A/21
pt.7). The aforementioned relocation was effective from 9 April 2020. Since the
major part of work under Contract No. KL/2014/03 has been completed and
monitoring works conducted by the ET of Contract No. KL/2014/03
was determined
to be ceased, the impact monitoring within the Kai Tak area was
then handed over to the ET of Contract No. ED/2018/04 on 1 August 2020.The
monitoring location has been reviewed and updated to obtain the data with
higher representative based on several conditions, such as distance between
monitoring location and the sensitive receiver, non-project related
interference, obstruction to the construction works on site and the power
supply problem. The monitoring location KTD1a and KER1b has been updated to the
monitoring location KTD1 and KER1 on 3 August 2020, where are the original
location as proposed in the EM&A manual (AEIAR-174/2013). And the
monitoring location KTD2c was remained unchanged after the aforementioned
review. Location
KTD2c was then further relocated to location KTD2d, the proposal of such
relocation was submitted on 9 March 2021 and was approved by EPD on 27
March 2021 (EPD reference: ( ) in EP2/K19/A/21 pt.8). The
aforementioned relocation was effective from 24 May 2021. The
impact monitoring for the three stations KTD1, KTD2d and KER1 are currently
conducted by the ET of T2 Main Works
Monitoring
Works in Cha Kwo Ling under EP-451/2013
1.5
The environmental impact of the remaining works in Cha Kwo Ling,
under EP-451/2013, shall be monitored at the two proposed stations, namely
CKL1, CKL2, in accordance to the EM&A Manual (AEIAR-174/2013).
The impact monitoring for the two proposed stations shall be conducted by the
ET of T2 Main Works.
1.6
Cinotech Consultants Ltd. Was designated as the Environmental Team (ET) to
undertake the EM&A
works for “Trunk Road T2 and Infrastructure Works for Developments at the
Former South Apron” (hereinafter called the “Project”) and “Trunk Road T2 –Traffic Control & Surveillance System (TCSS) and
Associated Works”.
1.7
This is the 60th Monthly EM&A Report which summarises
the impact monitoring results and audit findings for the EM&A programme
during the reporting period in February
2025.
1.8
Different Parties with different
levels of involvement in the Project organization include:
·
Permit Holder – Civil Engineering and Development Department
(CEDD)
·
Supervisor Representative – Hyder-Meinhardt
Joint Venture (HMJV)
·
Environmental Team (ET) – Cinotech Consultants Limited (Cinotech)
·
Independent Environmental Checker (IEC) – Ramboll Hong Kong Limited
(Ramboll)
·
Contractor – Bouygues Travaux Publics (BTP) (For ED/2018/04) & GTECH
Services (Hong Kong) Limited (For ED/2020/03)
1.9
The key contacts of the Project are shown in Table 1.1.
Table 1.1 Key
Project Contacts
Party |
Role |
Contact Person |
Phone No. |
CEDD |
Permit Holder |
Mr. Wong Chi Wai,
Tommy |
3842 7111 |
HMJV |
Supervisor
Representative |
Ms. Hazel Tang |
2149 8524 |
Cinotech |
Environmental Team |
Mr. KS Lee (ETL) |
2151 2091 |
Ms. Karina Chan |
2157 3880 |
||
Ramboll |
Independent
Environmental Checker |
Mr. YH Hui |
3465 2850 |
BTP |
Contractor
(ED/2018/04) |
Mr. Roy Leung |
6628 2685 |
GTECH |
Contractor
(ED/2020/03) |
Mr. Deacon Choi |
6038 3568 |
1.10
The Organizational Structure for Environmental Management is
shown in Figure 1.2.
Construction Activities undertaken during the Reporting Month
1.11
The major site activities undertaken in the reporting month included:
Table 1.2 Summary of
Key Construction Work in the Reporting Month
Contract
No. |
Project
Title |
Site
Activities |
ED/2018/04 |
Trunk Road T2 and Infrastructure
Works for Developments at South Apron |
·
WVB – ABWF works ·
WVB – E&M works ·
WVB – External works ·
DPR – GRC panel subframe
installation ·
DPR – Parapet Installation ·
SUS – E&M works ·
LSCC – RC Structure ·
LSCC – Backfilling ·
TSS – WB internal structure
from CP22 to CP26 ·
TSS – EB internal structure
up to CP22 ·
CP – TSS WB Tympanum
construction |
ED/2020/03 |
Trunk Road T2 – Traffic Control And
Surveillance System (TCSS) and Associated Works (1) |
·
WVB
–
Installation of TCSS
cable
containment,
cable laying, power distribution, installation of PA Speaker ·
WB &
EB Tunnel – Installation of cable containment ·
Material delivery for TCSS Sub- systems |
Notes: (1): No major
construction work was undertaken during reporting month. N/A: Not applicable |
1.12
The EM&A programme requires construction noise, air quality
monitoring and environmental site audit, etc. The EM&A requirements for
each parameter are described in the following sections, including:
·
All monitoring parameters;
·
Action and Limit levels for all environmental parameters;
·
Event Action Plans;
·
Environmental mitigation measures, as recommended in the Project EIA
Report.
1.13
The advice on the implementation status of environmental protection and
pollution control/mitigation measures is summarized in Section 10 of this report.
1.14
This report presents the monitoring results, observations, locations,
equipment, period, methodology and QA/QC procedures of the monitoring
parameters of the required environmental monitoring works and audit works for
the Project in February 2025.
Status of Environmental Licensing and Permitting
1.15
All permits/licenses
obtained for the Project are summarized in Table
1.3.
Table 1.3
Summary of Environmental License and Permit
Contract No. |
Permit / License No. |
Valid Period |
Status |
|
From |
To |
|||
Environmental Permit (EP) |
||||
N/A |
EP-451/2013 |
19 Sep 2013 |
N/A |
Valid |
Notification
pursuant to Air Pollution (Construction Dust) Regulation |
||||
ED/2018/04 |
Ref. No.: 451120 |
20 Nov 2019 |
N/A |
Valid |
ED/2020/03 |
Ref. No.: 483143 |
15 Aug 2022 |
N/A |
Valid |
Billing
Account for Construction Waste Disposal |
||||
ED/2018/04 |
A/C No.: 7036016 |
09 Dec 2019 |
N/A |
Valid |
ED/2020/03 |
A/C No.: 7043158 |
31 Jan 2022 |
N/A |
Valid |
Billing
Account for Vessel Disposal |
||||
ED/2018/04 |
|
|
|
|
A/C No.: 7037747
(Application No.: CEDD01260) |
26 Jan 2025 |
25 Apr 2025 |
Valid |
|
Construction
Noise Permit |
||||
ED/2018/04 |
CNP No. (For Launching Shaft and Barging Point): GW-RE0988-24 |
25 Aug 2024 |
24 Feb 2025 |
Valid until 24 Feb 25 |
CNP No. (For Depressed Road & Supporting Area): GW-RE1321-24 |
30 Oct 2024 |
30 Mar 2025 |
Valid |
|
CNP No. (For Launching Shaft and Barging Point): GW-RE1660-24 |
30 Dec 2024 |
29 Jun 2025 |
Valid |
|
Wastewater
Discharge License |
||||
ED/2018/04 |
WT00036183-2020
(For Depressed Road Area) |
27 Jul 2020 |
31 Jul 2025 |
Valid |
WT00039117-2021
(For Site Office and Support Area) |
28 Sep 2021 |
30 Sep 2026 |
Valid |
|
WT00036228-2020
(For Launching Shaft) |
10 Nov 2021 |
31 Jul 2025 |
Valid |
|
WT10001495-2023
(For TBM Consumable Storage Area) |
12 Mar 2024 |
31 Mar 2029 |
Valid |
|
Chemical
Waste Producer License |
||||
ED/2018/04 |
WPN:
5213-286-B2557-03 |
09 Mar 2020 |
N/A |
Valid |
Marine
Dumping Permit |
||||
ED/2018/04 |
EP/MD/25-047 |
01 Jan 2025 |
31 Mar 2025 |
Valid |
2
AIR Quality
2.1
According to the EM&A Manual (AEIAR-174/2013), 24-hour Total
Suspended Particulates (TSP) monitoring was conducted to monitor the air
quality for this Project. For regular impact monitoring, a sampling frequency
of at least once in every six days at all of the monitoring stations for
24-hour TSP monitoring. In case of complaints, 1-hour TSP monitoring should be
conducted at least three times in every six days when the highest dust impacts
are likely to occur. Appendix A shows the established Action/Limit
Levels for the environmental monitoring works.
2.2
Five designated monitoring stations were selected for air quality
monitoring programme. Table 2.1 describes the air quality monitoring
locations, which are also depicted in Figure 2.
2.3
The monitoring location at Kai Tak area has been reviewed and updated to
obtain the data with higher representative based on several conditions, such as
distance between monitoring location and the sensitive receiver, non-project
related interference, obstruction to the construction works on site and the
power supply problem. The monitoring location KTD1a and KER1b has been updated
to KTD1 and KER1 respectively, where are the original location as proposed in
the EM&A manual (AEIAR-174/2013). And the monitoring location KTD2c was
remained unchanged after the aforementioned review. Monitoring location KTD2c
was then further relocated to KTD2d after the review of status and location of
monitoring station conducted in between February and March 2021.
Table 2.1 Air Quality Monitoring Locations
Monitoring Stations |
Location |
KTD1 |
Centre of
Excellence in Paediatrics (Children’s Hospital) |
KTD2d |
Next to
the SOR Office of Trunk Road T2 in Kai Tak Area |
KER1 |
Future
Residential Development at Kerry Godown |
CKL1 |
Flat 121
Cha Kwo Ling Village |
CKL2 |
Flat 103
Cha Kwo Ling Village |
|
Monitoring Parameters and Frequency
2.4
Table 2.2 summarizes the monitoring parameters, monitoring period
and frequencies of impact air quality monitoring. The monitoring schedule is
shown in Appendix B.
Table 2.2 Frequency and Parameters of
Air Quality Monitoring
Monitoring
Stations |
Parameter |
Period |
Frequency |
KTD1, KTD2d, KER1, CKL1 & CKL2 |
1-hour TSP |
0700 – 1900 |
3 times
per 6 days (as required in case of complaints) |
KTD1, KTD2d, KER1, CKL1 & CKL2 |
24-hour TSP |
24 hours |
Once every 6 days |
|
2.5
High Volume Samplers (HVS) in compliance with the specification
stipulated in the EM&A Manual (AEIAR-174/2013), Section 2.2.1.4, were used
to carry out 24-hour TSP monitoring. Direct reading dust meter were also used
to measure 1-hour average TSP levels. The 1-hour sampling was determined by HVS
to check the validity and accuracy of the results measured by direct reading
method.
2.6
Wind data monitoring equipment was set at rooftop (about 41/F) of Yau
Lai Estate Bik Lai House, Lam Tin for logging wind speed and wind direction
such that the wind sensors were clear of obstructions or turbulence caused by
building. The wind data monitoring equipment was re-calibrated at least once
every six months and the wind directions were divided into 16 sectors of 22.5
degrees each. Wind data is attached in Appendix D.
2.7
Table 2.3 summarizes the equipment used for air quality
monitoring. Copies of calibration certificates are attached in Appendix C.
Table 2.3 Air Quality Monitoring Equipment
Equipment
|
Model |
Quantity |
HVS Sampler |
TISCH Model: TE-5170 (Serial
no. 0723, 1956, 10595, 1316, 5280) |
5 |
Calibrator |
TISCH Model: TE-5025A
(Serial no. 3864) |
1 |
Wind Anemometer |
Davis Weather Monitor II,
Model no. 7440 (Serial no. MC01010A44) |
1 |
1-hour TSP Monitoring
Measuring Procedures
2.8
The measuring procedures of the 1-hour dust meter are in accordance with
the Manufacturer’s Instruction Manual as follows:
(Sibata
Model No.: LD-3B/LD-5R)
·
The 1-hour dust meter is placed at least 1.3 meters above ground.
·
Set POWER to “ON” and make sure that the battery level was not flash or
in low level.
·
Allow the instrument to stand for about 3 minutes and then the cap of the
air sampling inlet has been released.
·
Push the knob at MEASURE position.
·
Set time/mode setting to [BG] by pushing the time setting switch. Then, start the background measurement by
pushing the start/stop switch once. It
will take 6 sec. to complete the background measurement.
·
Push the time setting switch to change the time setting display to
[MANUAL] at the bottom left of the liquid crystal display. Finally, push the
start/stop switch to stop the measuring after 1 hour sampling.
·
Information such as sampling date, time, count value and site condition
were recorded during the monitoring period.
Maintenance/Calibration
2.9
The following maintenance/calibration is required for the 1-hour dust
meter:
·
Check and calibrate the meter by HVS to check the validity and accuracy
of the results measured by direct reading method at 2-month intervals
throughout all stages of the air quality monitoring.
24-hour TSP Monitoring
Instrumentation
2.10
High volume samplers (HVS) (TISCH Model: TE-5170) complete with
appropriate sampling inlets was employed for 24-hour TSP monitoring. The sampler was composed of a motor, a filter
holder, a flow controller and a sampling inlet and its performance
specification complied with that required by USEPA Standard Title 40, Code of
Federation Regulations Chapter 1 (Part 50). Moreover, the HVS also met all the
requirements in Section 2.2 of the Annex II Specification.
2.11
The positioning of the HVS samplers are as follows:
·
A horizontal platform with appropriate
support to secure the samplers against gusty wind shall be provided;
·
No two samplers shall be placed less than 2
meters apart;
·
The distance between the sampler and an
obstacle, such as buildings, must be at least twice the height that the
obstacle protrudes above the sampler;
·
A minimum of 2 metres of separation from
walls, parapets and penthouses is required for rooftop samplers;
·
A minimum of 2 metres of separation from any
supporting structure, measured horizontally is required;
·
No furnace or incinerator flue is nearby;
·
Airflow around the sampler is unrestricted;
·
The sampler is more than 20 metres from the
dripline;
·
Any wire fence and gate, to protect the
sampler, shall not cause any obstruction during monitoring;
·
Permission must be obtained to set up the
samplers and to obtain access to the monitoring stations; and
·
A secured supply of electricity is needed to
operate the samplers.
Operating/analytical procedures for the operation
of HVS
2.12
Operating/analytical procedures for the air quality monitoring are
highlighted as follows:
·
Prior to the commencement of the dust sampling, the flow rate of the
high-volume sampler was properly set (between 0.6 m3/min.
and 1.7 m3/min.) in accordance with the EM&A manual (AEIAR-174/2013).
The flow rate shall be indicated on the flow rate chart.
·
For TSP sampling, fiberglass filters with a
collection efficiency of > 99% for particles of 0.3μm diameter were
used.
·
The power supply was checked to ensure the
sampler worked properly. On sampling,
the sampler was operated for 5 minutes to establish thermal equilibrium before
placing any filter media at the designated air monitoring station.
·
The filter holding frame was then removed by
loosening the four nuts and a weighted and conditioned filter was carefully
centered with the stamped number upwards, on a supporting screen.
·
The filter was aligned on the screen so that
the gasket formed an airtight seal on the outer edges of the filter. Then the filter holding frame was tightened
to the filter holder with swing bolts. The applied pressure should be
sufficient to avoid air leakage at the edges.
·
The shelter lid was closed and secured with
the aluminium strip.
·
The timer was then programmed. Information was recorded on the record sheet,
which included the starting time, the weather condition and the filter number
(the initial weight of the filter paper can be found out by using the filter
number).
·
After sampling, the filter was removed and
sent to the HOKLAS laboratory (High Precision Chemical Testing Ltd.) for
weighing. The elapsed time was also
recorded.
·
Before weighing, all filters were
equilibrated in a conditioning environment for 24 hours. The conditioning
environment temperature should be between 25°C and 30°C and not vary by more
than ±3°C; the relative humidity (RH) should be < 50% and not vary by more
than ±5%. A convenient working RH is 40%.
Maintenance/Calibration
2.13
The following maintenance/calibration is required for the HVS:
·
The high-volume motors and their accessories
were properly maintained. Appropriate maintenance such as routine motor brushes
replacement and electrical wiring checking were made to ensure that the
equipment and necessary power supply are in good working condition.
·
High volume samplers were calibrated at
bi-monthly intervals using TE-5025A Calibration Kit throughout all stages of the air
quality monitoring.
2.14
Impact air quality monitoring was conducted at five monitoring stations
as scheduled. The monitoring schedule is shown in Appendix B.
2.15
No Action and no Limit Level exceedance was recorded for 24-hour TSP
monitoring in the reporting month. No exceedance of 24-hour TSP were considered
as project related and no exceedance of 24-hour TSP were
considered as non-project related. Details of the exceedance are
presented in Appendix M.
2.16
The air temperature, relative humidity, and the precipitation data were
obtained from daily extracts of Hong Kong Observatory Climate Information
Service. This weather information for the reporting month is summarized in Appendix
D.
2.17
The monitoring data and graphical presentations of 24-hour TSP
monitoring results are shown in Appendix F.
2.18
According to field observations observed in the reporting period, the
major dust source identified at the designated air quality monitoring stations
are as follows:
Table
2.4 Major Dust Source during Air
Quality Monitoring
Monitoring
Stations |
Major Dust Source |
KTD 1 - Centre of
Excellence in Paediatrics (Children’s Hospital) |
·
Project related construction activities
(i.e., Loading and unloading of C&D wastes, drilling, crushing of
material); ·
Vehicle movement in the site; ·
Construction activities at the nearby
construction sites of New Acute Hospital; and, ·
Road traffic along Shing Fung Road, Shing
Cheong Road, Cheung Yip Street, Kai Hing Road and Kwun Tong Bypass. |
KER 1 – Future Residential Development at Kerry Godown |
|
KTD 2d – Next to
the SOR Office of Trunk Road T2 in Kai Tak Area |
·
Project related construction activities
(i.e., Loading and unloading of C&D material, crushing of material); ·
Vehicle movement in the site; and, ·
Non-project related construction activities
(i.e excavating work, Loading and unloading of C&D wastes at the nearby
construction site of Additional District Cooling System at Kai Tak
Development, Paul Y. Engineering.) |
CKL1 - Flat 121 Cha Kwo Ling Village |
·
Road Traffic along Cha Kwo Ling Road |
CKL2 - Flat 103 Cha Kwo Ling Village |
·
Road Traffic along Cha Kwo Ling Road |
|
Comparison of EM&A Result with EIA Prediction
2.19
The air monitoring data was compared with the predictions in Table 4.14
of EIA Report, AEIAR-174/2013 (as approved in 2013) as summarised in Table
2.6 for 24-hour TSP.
Table 2.6 Comparison of 24-hr TSP Monitoring Data
with Predictions in EIA Report
Monitoring Stations |
ASR ID |
Predicted Maximum 24-hr TSP Concentration in EIA Report (AEIAR-174/2013), μg/m3 |
Maximum 24-hr TSP Concentration in the Reporting Month |
KTD 1 - Centre of Excellence in Paediatrics (Children’s
Hospital) |
KTD3 |
126 |
47.9 |
KTD 2d – Next to
the SOR Office of Trunk Road T2 in Kai Tak Area |
N/A (1) |
N/A (1) |
92.6 |
KER 1 – Future Residential Development at Kerry Godown |
KTD6 |
169 |
60.8 |
CKL1 - Flat 121 Cha Kwo Ling Village |
N/A (1) |
N/A (1) |
136.4 |
CKL2 - Flat 103 Cha Kwo Ling Village |
N/A (1) |
N/A (1) |
120.4 |
Remarks:
(1)
No 24-hr TSP
concentration was predicted in EIA Report (AEIAR-174/2013)
2.20
In the reporting month, the 24-hour TSP concentration at KER1 and KTD1
were lower than the prediction in the EIA Report, AEIAR-174/2013 (as approved
in 2013). No Action and Limit level exceedance for 24-hour TSP was recorded in
the reporting period.
Monitoring Requirement
3.1
According to the
EM&A Manual (AEIAR-174/2013), construction noise monitoring was
conducted to monitor the construction noise arising from the construction
activities. The regular monitoring frequency for each monitoring station shall
be on a weekly basis and conduct one set of measurements between 0700 and 1900
hours on normal weekdays. Appendix A
shows the established Action and Limit Levels for the environmental monitoring
works.
3.2
Noise monitoring was conducted at five designated monitoring stations,
namely KTD1, KTD2d, KER1, CKL1 and CKL2 in the reporting period. Table 3.1 and Figure 2 show the locations of these stations.
3.3
The monitoring location at Kai Tak area has been reviewed and updated to
obtain the data with higher representative based on several conditions, such as
distance between monitoring location and the sensitive receiver, non-project
related interference, obstruction to the construction works on site and the
power supply problem. The monitoring location KTD1a and KER1b has been updated
to KTD1 and KER1 respectively, where are the original location as proposed in
the EM&A manual (AEIAR-174/2013). And the monitoring location KTD2c was
remained unchanged after the aforementioned review. Monitoring location KTD2c
was then further relocated to KTD2d after the review of status and location of
monitoring station conducted in between February and March 2021.
Table 3.1 Noise
Monitoring Stations
Monitoring Stations |
Location |
KTD1 |
Centre of
Excellence in Paediatrics (Children’s Hospital) |
KTD2d |
Next to
the SOR Office of Trunk Road T2 in Kai Tak Area |
KER1 |
Future Residential Development at Kerry Godown |
CKL1 |
Flat 121
Cha Kwo Ling Village |
CKL2 |
Flat 103
Cha Kwo Ling Village |
|
Monitoring
Parameters, Frequency and Duration
3.4
Table 3.2 summarizes the monitoring
parameters, frequency and total duration of monitoring. The noise monitoring schedule is shown in Appendix B.
Table 3.2 Frequency
and Parameters of Noise Monitoring
Monitoring Stations |
Time Period |
Duration |
Frequency |
Parameter |
Measurement |
KTD1 |
0700-1900 hrs on normal weekdays |
30 minutes |
Once per
week |
L10(30
min.) dB(A) L90(30
min.) dB(A) Leq(30
min.) dB(A) |
Façade Measurement |
KTD2d |
Free Field Measurement |
||||
KER1 |
Free Field Measurement |
||||
CKL1 |
Free Field Measurement |
||||
CKL2 |
Free Field Measurement |
3.5
Integrating Sound Level Meter was used for impact noise monitoring. The
meters were Type 1 sound level meter capable of giving a continuous readout of
the noise level readings including equivalent continuous sound pressure level
(Leq) and percentile sound pressure level (Lx) that also
complied with International Electrotechnical Commission Publications 651:1979
(Type 1) and 804:1985 (Type 1) specifications. Table 3.3 summarizes the noise monitoring equipment
being used within the reporting period. Copies of calibration certificates are
attached in Appendix G.
Table 3.3 Noise Monitoring Equipment
Equipment |
Model
|
Quantity |
Integrating Sound Level Meter |
BSWA 308 (Serial no. 570187, 580238, 580156) SVAN 957 (Serial no. 23851) |
4 |
Calibrator |
AWA6021A (Serial no.1023253, 1023064) |
2 |
Monitoring
Methodology and QA/QC Procedure
3.6
The monitoring procedures are as follows:
·
The monitoring station was normally be at a
point 1m from the exterior of the sensitive receivers building façade and be at
a position 1.2m above the ground.
·
For free field measurement, the meter was positioned away from any
nearby reflective surfaces. All records for free field noise
levels were adjusted with a correction of +3 dB(A).
·
The battery condition was checked to ensure the correct
functioning of the meter.
·
Parameters such as frequency weighting, the time weighting and the
measurement time were set as follows:
-
Frequency weighting: A
-
Time weighting: Fast
-
Time measurement: 30 minutes
·
Prior to and after each noise measurement, the meter was calibrated
using a Calibrator for 94.0 dB at 1000 Hz. If the difference in the calibration level before and
after measurement was more than 1.0 dB, the measurement would be considered
invalid and repeat of noise measurement would be required after re-calibration
or repair of the equipment.
·
The wind speed was frequently checked with the portable wind meter.
·
At the end of the monitoring period, the Leq, L90
and L10 were recorded.
In addition, site conditions and noise sources were recorded on a standard
record sheet.
·
Noise monitoring would be cancelled in the presence of fog, rain, and
wind with a steady speed exceeding 5 m/s, or wind with gusts exceeding 10 m/s.
Supplementary
monitoring would be provided to ensure sufficient data would be
obtained.
3.7
The microphone head of the sound level meter and calibrator were cleaned
with a soft cloth at quarterly intervals.
3.8
The sound level meter and calibrator were checked and calibrated at
yearly intervals.
3.9
Immediately prior to and following each noise measurement the accuracy
of the sound level meter was checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements were accepted as
valid only if the calibration levels from before and after the noise
measurement agree to within 1.0 dB.
3.10
Impact noise monitoring was conducted at five monitoring stations as
scheduled. The monitoring schedule is shown in Appendix B. No Action and Level exceedance was recorded for day
time construction noise monitoring in the reporting month.
3.11
Noise monitoring results and graphical presentations are shown in Appendix H.
3.12
According to field observations observed in the reporting period, the
major noise sources identified at the noise monitoring stations are shown in Table 3.4.
Table 3.4
Other Noise Source Identified during Noise Monitoring
Monitoring
Stations |
Major Noise Source |
KTD 1 |
·
Project related construction activities
(Loading and unloading of C&D waste, travel of vehicles, use of PME and
other plants, and other construction activities); ·
Vehicle movement in the site; ·
Road traffic along Shing Cheong Road; and, ·
Non-project related construction activities
at the nearby construction site of New Acute Hospital. |
KTD 2d |
·
Project related construction activities
(Loading and unloading of C&D waste, travel of vehicles, use of PME and
other plants, and other construction activities); ·
Vehicle movement in the site; and, ·
Non-project related construction
activities. (i.e excavating work, Loading and unloading of C&D wastes at
the nearby construction site of Additional District Cooling System at Kai Tak
Development, Paul Y. Engineering.) |
KER 1 |
·
Road traffic along Kai Hing Road. ·
Project related construction activities
(Travel of vehicles, use of PME and other plants, and other construction
activities) |
CKL1 |
·
Road traffic along Cha Kwo Ling Road. |
CKL2 |
·
Road traffic along Cha Kwo Ling Road |
3.13
The baseline noise level and the Noise Limit Level at each designated
noise monitoring station are presented in Table 3.5.
Table 3.5 Baseline Noise Level and Noise Limit
Level for Monitoring Stations
Monitoring Stations |
Baseline Noise Level, dB (A) |
Noise Limit Level, dB (A) (at 0700 – 1900 hrs on normal weekdays) |
KTD1 |
78 |
75 |
KTD2d |
64 |
|
KER1 |
65 |
|
CKL1 |
72.4 |
|
CKL2 |
71.4 |
Comparison
of EM&A Result with EIA Prediction
3.14
The noise monitoring data was compared with the predictions in Table
5.13 of EIA Report (AEIAR-174/2013) as summarised in Table 3.6.
Table 3.6
Maximum Predicted Mitigated Construction Noise Levels in EIA Report
Monitoring Stations |
NSR ID |
Maximum Predicted Mitigated
Construction Noise Levels in EIA Report (AEIAR-174/2013), dB(A) |
Maximum Construction
Noise Levels in the Reporting Month |
KTD1 - Centre of Excellence in Paediatrics
(Children’s Hospital) |
KTD1 |
74 |
71.3 |
KTD2d – Next to
the SOR Office of Trunk Road T2 in Kai Tak Area |
N/A (1) |
N/A (1) |
63 |
KER1 – Future Residential Development at Kerry
Godown |
KER1 |
75 |
73 |
CKL1 - Flat 121 Cha Kwo Ling Village |
CKL4 |
71 |
74 |
CKL2 - Flat 103 Cha Kwo Ling Village |
CKL5 |
69 |
74 |
Remarks: (1): No Maximum Predicted Mitigated Construction Noise
Levels was predicted in EIA Report (AEIAR-174/2013) |
3.15
The result at CKL1, CKL2 were higher than the maximum predicted
mitigated construction noise level in the EIA Report, AEIAR-174/2013 (as
approved in 2013), this may be due to fluctuations of traffic flow along Cha
Kwo Ling Road. Besides, the result at KTD1 and KER1 were lower than the maximum
predicted mitigated construction noise level in the EIA Report. No Action and
Limit Level exceedance were recorded in the reporting period.
4.1
According to Section 4.3.1.1 of EM&A Manual (AEIAR-174/2013), no
water quality monitoring is required during the construction phase.
4.2
According to Section 4.3.1.5 of EM&A
Manual (AEIAR-174/2013), compliance site audits are to be
undertaken by the Engineer and ET and escorted by the Contractor to ensure that
a valid discharge license has been issued by the EPD prior to the discharge of
the effluent from the construction activities of the Project site. Monitoring
of the quality of the treated effluent from the works areas should be carried
out in accordance with the Water Pollution Control Ordinance (WPCO) license.
The audit results reflect whether the effluent quality is in compliance with
the discharge license requirements, the summaries of site audits are attached in Appendix I.
4.3
In the event of non-compliance, the responsibilities of the relevant
parties are detailed in the Event / Action plan attached in Appendix J.
5.1
According to Section 5.3.1.1 of EM&A
Manual (AEIAR-174/2013), ET will be required to undertake
audit of good site practice for habitat protection as detailed below. The
summaries of site audits are attached in Appendix
I.
·
Avoid damage and disturbance to the remaining and surrounding natural
habitat;
·
Ensure placement of equipment is within designated areas within the
existing disturbed land;
·
Ensure construction activities are restricted to within the proposed
works boundary;
·
Ensure spoil heaps are be covered at all times;
·
Ensure that disturbed areas are reinstated immediately after completion
of the works; and
·
Ensure enhancement planting works undertaken.
6
fisheries
6.1
According to Section 6.3.1.2 of EM&A
Manual (AEIAR-174/2013), no specific fisheries monitoring and
audit programme is required during the construction phase.
6.2
The implementation of the water quality mitigation measures stated in
the Water Quality Impact Assessment (Refer to Section 6 of the EIA Report (AEIAR-174/2013)) will be audited as part
of the EM&A procedures during the construction period and the details are
presented in Section 4.2 of this
Report. The summaries of site audits are attached in Appendix I.
7.1
According to the EM&A Manual (AEIAR-174/2013), a series of mitigation
measures were recommended to ameliorate the landscape and visual impacts of the
Project. The mitigation measures for construction stage are summarized in Table 7.1 below and provided in Appendix K:
Table 7.1
Construction Phase Landscape and Visual Mitigation Measures
ID No. |
Landscape and Visual
Mitigation Measure |
CM1 |
All works shall be carefully designed to
minimize impacts on existing landscape resources and visually sensitive receivers.
Existing trees within works area shall be
retained and protected. |
CM2 |
Existing
trees of good quality and condition that are unavoidably affected by the
works should be transplanted. |
CM3 |
Not used. |
CM4 |
Not used. |
CM5 |
Large temporary stockpiles of excavated
material shall be covered with unobtrusive sheeting to prevent dust and
dirt spreading to adjacent landscape areas and vegetation, and to create a neat
and tidy visual appearance. |
CM6 |
Construction plant and building material
shall be orderly and carefully stored in order to create a neat and tidy visual
appearance |
CM7 |
Erection of decorative screen hoarding
should be designed to be compatible with the existing urban context. |
CM8 |
All lighting in construction site shall be
carefully controlled to minimize light pollution and night-time glare to nearby
residences and GIC user. The contractor shall consider other security measures,
which shall minimize the visual impacts. |
7.2
A specialist Landscape Sub-Contractor should be employed by the
Contractor for the implementation of landscape construction works and
subsequent maintenance operations during the establishment period. It is
proposed that the planting works will be on-site and the planting should be
completed during the construction contract. The monitoring of the planting
establishment should be undertaken for a 12-month period which could extend
throughout the Contractor’s one-year maintenance period, which will be within the
first operational year of the Project.
7.3
All measures undertaken by both the Contractor and the specialist
Landscape Sub-Contractor during the construction phase and first year of the
operational phase shall be audited by a Registered Landscape Architect (RLA),
as a member of the Environmental Team (ET), on a regular basis to ensure
compliance with the intended aims of the measures. To fulfil the aforementioned
requirements, on-site landscape and visual mitigation measures were audited by
RLA in the reporting month.
7.4
According to Section 7.3.1.2 of the EM&A Manual (AEIAR-174/2013),
site audits shall be undertaken at least once every two weeks throughout the
construction period to monitor and audit the timely implementation of landscape
and visual mitigation measures within the site boundaries of this Project.
7.5
The broad scope of the audit is detailed below but should also be
undertaken with reference to the more specific checklist provided in Table
7.2. The summaries of site audits are attached in Appendix I:
·
The extent of the agreed works areas should
be regularly checked during the construction phase. Any trespass by the
Contractor outside the limit of the works, including any damage to existing
trees and soft landscape areas shall be prohibited;
·
the progress of the engineering works should
be regularly reviewed on site to identify the earliest practical opportunities
for the landscape works to be undertaken;
·
all existing trees and vegetation within the
study area which are not directly affected by the works are retained and
protected;
·
the methods of protecting existing vegetation
proposed by the Contractor are acceptable and enforced;
·
preparation, lifting transport and
re-planting operations for any transplanted trees;
·
all landscaping works are carried out in
accordance with the specifications;
·
the planting of new trees, shrubs,
groundcover, climbers, ferns, grasses and other plans,
together with the replanting of any transplanted trees are carried out properly and
within the right season; and
·
all necessary horticultural operations and
replacement planting are undertaken throughout the Establishment Period to ensure
the healthy establishment and growth of both transplanted trees and all
newly established plants.
Table 7.2
Construction Phase Audit Checklist for Landscape and Visual
Mitigation
Measures
Area of Works |
Items to be Monitored |
Advance planting |
Monitoring of implementation
and maintenance of planting, and against possible incursion, physical damage,
fire, pollution, surface erosion, etc. |
Protection of all trees and existing soft landscape
areas to be retained |
Identification and demarcation of trees / vegetation to
be retained, erection of physical protection (e.g. fencing), monitoring
against possible incursion, physical damage, fire, pollution, surface
erosion, etc. |
Clearance of existing vegetation |
Identification and demarcation of trees / vegetation to
be cleared, checking of extent of works to minimise damage, monitoring of
adjacent areas against possible incursion, physical damage, fire, pollution,
surface erosion, etc. |
Pruning of trees |
Identification and demarcation of trees / vegetation to
be pruned, monitoring of extent of pruning to minimise damage, timing of
operations, implementation of all stages of preparatory and pruning works,
and maintenance of pruned vegetation, etc. |
Plant supply |
Monitoring of operations relating to the supply of
specialist plant material (including the collecting, germination and growth
of plants from seed) to ensure that plants will be available in time to be
used within the construction works. |
Soiling, planting, etc. |
Monitoring of implementation and maintenance of soiling
and planting works and against possible incursion, physical damage, fire,
pollution, surface erosion, etc. |
Site fencing and hoarding |
Implementation and maintenance, to ensure compliance
with agreed designs and check that it matches the surrounding environment and
does not cause visual intrusion. |
Architectural treatment of engineering works. |
Implementation and maintenance of mitigation measures,
to ensure compliance with agreed designs as applicable. |
Establishment Works |
Monitoring of implementation of maintenance operations
during Establishment Period. |
7.6
In the event of non-compliance, the responsibilities of the relevant parties
are detailed in the Event / Action plan attached in Appendix J.
7.7
In the reporting month, no non-compliance of the landscape and visual
mitigation measures was recorded by RLA.
8.1
According to Section 8.3.1.1 of EM&A Manual (AEIAR-174/2013), as a
precautionary measure, it is recommended that if any antiquity or supposed
antiquity is discovered during the course of the excavation works undertaken by
the Contractor, the discovery shall be reported to the AMO immediately and all
necessary measures taken to preserve it.
8.2
According to Section 8.3.1.2 of EM&A Manual (AEIAR-174/2013), no
EM&A is required during the construction and operational phase.
9.1
According to Section 9.3.1.1 of EM&A Manual (AEIAR-174/2013), the effective management
of waste arisings during the construction phase will be monitored through the
site audit programme. Regular audits and site inspections should be carried out
by the Engineer, ET and Contractor to ensure that the recommended good site
practices and other mitigation measures are implemented by the Contractor. The
summaries of site audits are attached in Appendix
I.
9.2
According to Sections 9.3.1.3 and 9.3.1.4 of EM&A Manual (AEIAR-174/2013), documents including licenses,
permits, disposal and recycling records should be reviewed and audited during
site audits for the compliance with the legislation and contract requirements
to ensure proper records are being maintained and procedures undertaken in
accordance with the Waste Management Plan.
9.3
With reference to the relevant handing records
of this Project, the quantities of different types of waste generated in the
reporting month are summarized and presented in the Appendix O.
10.1
Site audits were carried out on a weekly basis to monitor the timely
implementation of proper environmental management practices and mitigation
measures in the Project site. The summaries of site audits are attached in Appendix I.
10.2
Site audits for each contract were conducted as follows.
·
ED/2018/04 – Site audit was conducted on 06, 13, 20
& 27 February
2025 in the
reporting month. Site inspection of the IEC was conducted on 27 February
2025. No non-compliances were
observed during site audits.
·
ED/2020/03 – Site audit was conducted on 06, 14, 20
& 27 February
2025 in the
reporting month. Site inspection of the IEC was conducted on 14
February 2025.
No non-compliance was observed during the site audits.
Implementation Status of Environmental
Mitigation Measures
10.3
According to Environmental Permits, the approved EIA Reports (Register
No.: AEIAR-174/2013 and AEIAR-173/2013), and the EM&A Manuals of the
Project (AEIAR-174/2013 and AEIAR-173/2013), the mitigation measures
detailed in the documents are recommended to be implemented during the
construction phase. An Environmental Mitigation Implementation Schedule (EMIS)
is provided in Appendix K.
10.4
The ET weekly site inspections were carried out during the reporting
month and the observations and recommendations are summarized in Table 10.1. Refer to Appendix I for the site inspection
summary reports in the reporting month.
Table 10.1
Observations and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Air
Quality |
N/A |
There was no observation in the reporting
period. |
N/A |
Noise |
N/A |
There was no observation in the reporting
period. |
N/A |
Water
Quality |
27 Feb
2025 |
Stagnant
water was observed. |
Follow up in the next reporting month. |
Ecology |
N/A |
There was no observation in the reporting
period. |
N/A |
Landscape
and Visual |
N/A |
There was no observation in the reporting
period. |
N/A |
Waste/
Chemical Management |
N/A |
There was
no observation in the reporting period. |
N/A |
Permits
/Licences |
N/A |
There was no observation in the reporting
period. |
N/A |
Implementation
Status of Event and Action Plans
10.5
The Event and Action Plans for air quality, construction noise, and
landscape and visual are presented in Appendix J.
Air Quality Monitoring
·
No Action and no Limit Level exceedance for 24-hour TSP monitoring was
recorded.
Construction Noise Monitoring
·
No Action and Limit Level exceedance was recorded in the reporting
month.
Landscape and Visual
·
No landscape and visual non-conformity were recorded.
Status of Required Submission under
Environmental Permit
10.6
According the Section 11.3.2.1 (c) of the EM&A Manual
(AEIAR-174/2013), status of required submission under EP-451/2013 during the
reporting period are summarized in Table
10.2.
Table 10.2 Status of Required Submission under
Environmental Permit
EP Condition |
Submission |
Submission Date |
EP-451/2013 |
||
Condition
2.3 |
Management
Organization of Main Construction Companies for ED/2018/04 |
20 January 2020 |
Condition
2.3 |
Management
Organization of Main Construction Companies for ED/2020/03 |
21 March 2023 |
Condition
2.4 |
Design
Drawing of the Project |
20 January 2020 |
Condition
2.5 |
Landscape
Mitigation Plan (Rev. F) |
25 November 2022 |
Condition
2.10 (a) |
Supplementary
Contamination Assessment Plan |
18 December 2015 |
Condition
2.10 (b) |
Supplementary
Contamination Assessment Report |
6 December 2016 |
Condition
3.3 |
Updated
Baseline Monitoring Report |
3 November 2020 |
Condition
3.4 |
Monthly
EM&A Report (January 2025) for ED/2018/04 and ED/2020/03 |
13 February 2025 |
11
Environmental non-conformance
Summary of Complaint, Warning,
Notification of any Summons and Successful Prosecution
11.1
The summaries of environmental complaint, warning, summon and
notification of successful prosecution for the Project is presented in Appendix L.
11.2
The summary of exceedance record in the reporting month is shown in Appendix
M.
11.3
No non-conformity was recorded for landscape and visual inspections
conducted in the reporting month.
12.1
Tentative construction programmes for the next three months are provided
in Appendix N.
12.2
Major site activities undertaken for the coming months and the key
environmental issues are summarized as follows:
Table 12.1 Summary Table for Site Activities and the Key
Environmental Issues in the next Reporting Period
Contract
No. and Project Title |
Site Activities (March 2025) |
Key
Environmental Issues |
ED/2018/04
- Trunk Road T2 and Infrastructure Works for Developments at South Apron |
·
WVB – ABWF works ·
WVB – E&M works ·
WVB – External works ·
DPR – GRC panel subframe
installation ·
DPR – Parapet installation ·
DPR – Sign gantry erection ·
SUS – E&M works ·
LSCC – RC Structure ·
LSCC – Backfilling ·
TSS – WB internal structure
from CP22 to CP26 ·
TSS – EB internal structure
up to CP22 ·
CP – TSS WB Tympanum
construction |
·
Wheel washing bay at site exits; ·
Temporary noise barriers for PMEs; ·
Sedimentation tank for settling muddy water; and ·
Make sure open stockpiles are covered during rainstorm. |
ED/2020/03
- Trunk Road T2 - Traffic Control And Surveillance System (TCSS) and
Associated Works(1) |
·
Project signboard in works
area |
·
The waste should be removed
regularly and litter free. ·
The storage area should be
kept tidy. |
Notes: (1): No major construction
work was undertaken during reporting month. N/A: Not
applicable |
12.3
The tentative environmental monitoring schedule for the next three
months are shown in Appendix B.
13
Conclusions and recommendations
13.1
This is the 60th Monthly EM&A Report which
presents the EM&A works undertaken during the reporting month in accordance
with the EM&A Manual (AEIAR-174/2013)
and the
requirement under EP.
Air Quality Monitoring
13.2
No Action and no Limit Level exceedance was recorded for 24-hour TSP
monitoring in the reporting month.
Construction Noise Monitoring
13.3
No Limit Level exceedance was recorded for day-time construction noise
monitoring in the reporting month.
13.4
No Action Level exceedance was recorded in the reporting month.
Site Audit
13.5
Four (4) ET joint weekly environmental site inspections were conducted
for the Contact No. ED/2018/04 in the reporting month.
13.6
Four (4) ET joint environmental site inspections were conducted for the
Contact No. ED/2020/03 in the reporting month.
Complaint, Notification of
Summons and Successful Prosecution
13.7
No environmental complaint was received in the reporting
month. No notifications of summons and successful prosecutions were received in
the reporting month.
13.8
According to the environmental audit performed in the reporting month,
the following recommendations was made:
ED/2018/04
Water Quality
·
Ponding water should be removed.